Skip to main content
DistrictCampusDirectory
CAMPUS

Update on High School project: April 2017


Posted Date: 06/13/2017

Update on High School project: April 2017

Schedule:

  • Construction drawings 100% complete as of April 10
  • April 11-May 2:  Bid package period.  Bid opening May 2, 2:00 pm
  • Presentation of Guaranteed Maximum Price to the district staff-May 10
  • District awards GMP at May 16 special called board meeting
  • Start construction June 5
  • Substantial completion- August 2018

The contractor will begin fencing and staging equipment in late May. Student parking lot will not be available for the 2017-18 school year. Buses will load and unload on the north side of the building.

The bond oversight committee met on April 11. Stantec staff showed the 3D views of the building and shared construction materials with them and were available for questions.