PROJECT SCHEDULE

INITIAL PROJECT MILESTONE SCHEDULE

 

Activity                                                                                                                           Date Completed 

 

Owner Approves Facility Program Phase                                                                          August 12, 2016

 

Schematic Design Phase

         Authorize A/E Start                                                                                              August 12, 2016

         Submit 95% SD Documents for Owner Review & Cost Estimating                             September 26, 2016

         Joint Review for Owner Comments                                                                        September 28, 2016

         Owner Review of Cost Estimate & Approval of Schematic Design                              October 10, 2016

 

Design Development Phase 

         Authorize A/E Start                                                                                              October 10, 2016

         Submit 100% DD Documents for Owner Review & Cost Estimating                           December 15, 2016

         Joint Review for Owner Comments                                                                        January 4, 2017

         Owner Review of Cost Estimate & Approval of Design                                             January 19, 2017

         

Construction Documents Phase 

         Authorize AE to Start                                                                                           January 19, 2017

         A/E Submit 50% CD's for Owner Review & cost Estimating                                      February 15, 2017

         Joint Review for Owners Comments                                                                      February 22, 2017

         Review of 50% CD Cost Estimate                                                                          March 1, 2017

         A/E Submit 95% CD's for Review & Cost Estimating                                                March 23, 2017

         Joint Review for Owner Comments                                                                       April 6, 2017

         Owner Review of Cost Estimate & Approval of 100% CD's                                       April 7, 2017

         Issue Construction Documents for Bidding                                                             April 10, 2017

         Receive Subcontractor Proposals                                                                           May 2, 2017

         Bonham ISD Approve Guaranteed Maximum Price                                                   May 15, 2017

         

Construction Phase Activities 

 

         NTP for Construction                                                                                             May 16, 2017

         Project Substantial Completion                                                                               August 3, 2018