PROJECT SCHEDULE
INITIAL PROJECT MILESTONE SCHEDULE
Activity Date Completed
Owner Approves Facility Program Phase August 12, 2016
Schematic Design Phase
Authorize A/E Start August 12, 2016
Submit 95% SD Documents for Owner Review & Cost Estimating September 26, 2016
Joint Review for Owner Comments September 28, 2016
Owner Review of Cost Estimate & Approval of Schematic Design October 10, 2016
Design Development Phase
Authorize A/E Start October 10, 2016
Submit 100% DD Documents for Owner Review & Cost Estimating December 15, 2016
Joint Review for Owner Comments January 4, 2017
Owner Review of Cost Estimate & Approval of Design January 19, 2017
Construction Documents Phase
Authorize AE to Start January 19, 2017
A/E Submit 50% CD's for Owner Review & cost Estimating February 15, 2017
Joint Review for Owners Comments February 22, 2017
Review of 50% CD Cost Estimate March 1, 2017
A/E Submit 95% CD's for Review & Cost Estimating March 23, 2017
Joint Review for Owner Comments April 6, 2017
Owner Review of Cost Estimate & Approval of 100% CD's April 7, 2017
Issue Construction Documents for Bidding April 10, 2017
Receive Subcontractor Proposals May 2, 2017
Bonham ISD Approve Guaranteed Maximum Price May 15, 2017
Construction Phase Activities
NTP for Construction May 16, 2017
Project Substantial Completion August 3, 2018